Southeast Florida
Kitchen Remodel in Palm Beach County, Florida
Permit requirements, inspections and modeled costs for kitchen remodel in unincorporated Palm Beach County. If your address falls inside a city, the municipal building department issues the permit instead.
Verified August 2026
Do you need a permit for kitchen remodel in Palm Beach County?
It depends
It depends on scope. Like-for-like cosmetic work in Unincorporated Palm Beach County is often exempt, but a permit is required as soon as you change structure, plumbing, electrical or the building envelope.
Budget $20,700 – $105,800 for the work itself (typically $44,300) plus $255–$1,215 in permit fees.
Palm Beach County cost model
| Budget scope | $20,700 |
|---|---|
| Typical project | $44,300 |
| Premium / complex | $105,800 |
| per kitchen | $20,700 – $105,800 |
| Permit fees | $255 – $1,215 |
| vs national baseline | +15% |
| Timeline | 6-12 weeks |
Inspections you should expect
- Rough plumbing and electrical
- Framing where walls change
- Final building inspection
What the county will ask for
- Permit application
- Floor plan showing changes
- Electrical and plumbing scope
- Contractor licensing
Cities inside the county that permit their own work
If the property is inside these municipalities, apply to the city rather than the county.
Statewide rules that apply here
Palm Beach County enforces the 8th Edition (2023) Florida Building Code, effective December 31, 2023. Local amendments can add requirements but cannot reduce the statewide minimum.
Frequently asked questions
Do I need a permit for a kitchen remodel?
Cosmetic replacement — cabinets in the same location, countertops, appliances, paint and flooring — typically does not require a permit. You do need one as soon as you move plumbing or electrical, add circuits, or alter walls.
How long does a kitchen remodel take?
A cosmetic refresh runs 3-5 weeks. A full gut with layout changes and permits typically runs 8-12 weeks, with cabinet lead time as the most common bottleneck.
Sources
Sources & verification
Last verified August 2026. Cost figures are modeled estimates based on national baselines adjusted for local labor and material pricing — they are not quotes. Permit rules change; confirm with the building department before starting work.